中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/66070
English  |  正體中文  |  简体中文  |  全文筆數/總筆數 : 80990/80990 (100%)
造訪人次 : 42717939      線上人數 : 1324
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜尋範圍 查詢小技巧:
  • 您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
  • 若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
  • 進階搜尋


    請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/66070


    題名: 臺北市污水下水道用戶接管 開口契約內容及執行案例之研究;The Research of Indefinite Delivery Contracts Implementation and Case Studies for Household Sewerage Pipes Connections of Taipei City
    作者: 李威宏;hung,lee wei
    貢獻者: 營建管理研究所在職專班
    關鍵詞: 公共工程;開口契約;設施維護;污水費;下水道;監造;Public construction;indefinite delivery contract;facility maintenance;Sewerage;Supervision
    日期: 2014-07-24
    上傳時間: 2014-10-15 17:28:18 (UTC+8)
    出版者: 國立中央大學
    摘要: 過去開口契約之研究,發現在最後建議中提到不同規模、性質之維護工作考量,其開口契約適用情形不一,仍有待進一步探討和歸納,並將特點和目的具體地融入開口契約範本,也建議機關可針對不同性質工作,訂定不同開口契約的基本架構,過去關於此之研究,甚少探討到污水工程開口契約,本研究適可補足過去之不足。因此,本研究以我國、美國、日本及新加坡四個國家之污水下水道(含污水費結構)、開口契約、監造業務為文獻回顧,並切入開口契約之問題:(1)以開口契約之制度面、執行面和結構性問卷訪談,以三個面向來探討開口契約與一般契約差異,訪談對象以主辦機關、監造廠商、施工廠商並設立專家組對與照組共17 人員做對照研究,就開口契約主要特性探討並減少開口契約履約可能發生之爭議。(2)並以污水工程開口契約交辦案中340 個執行案例,基於資料蒐集與取得之「完整性」和「發
    生機率」探討遭遇私地補償、中央天井、危建、管線障礙、既有人孔掩沒、地面高低差過大、老舊建物等七個障礙時可能衍生之問題、處理方式、主要問題態樣及最終目的為解決與對策。;ABSTRACT
    The past research of indefinite delivery contracts have discovered that different project sizes and
    characteristics affect the application of indefinite delivery contracts to the projects. They also
    suggested thatgovernment organizations can establish different indefinite delivery contract
    structures for the projects of different characteristics. However, past researches seldom discuss and
    analyze such topic on indefinite delivery contracts for sewerage construction. Therefore, this
    research focuses on the system, administration and implementation of indefinite delivery contracts
    for sewerage construction from the supervision perspective. This research starts with literature
    reviews of the current practices of sewer systems (including sewerage fee structure) in Taiwan,
    United States, Japan and Singapore as well as reviews of indefinite delivery contracts.The
    differences between indefinite delivery contracts and traditional contracts are then analyzed and
    discussed to understand the major characteristics of indefinite delivery contracts for sewerage. In
    addition, this research collects five real cases, which consist of seven different obstacles commonly
    encountered in the sewerage construction. These obstacles are compensation for private land,
    central skylight of buildings, dangerous buildings, underground pipeline barriers, submerged
    existing manholes, huge ground elevation difference, and old buildings. This research introduces
    these obstacles, and discusses and proposes meansand solutions to deal with these obstacles. All the
    discussions and analyses are validated through interviews with domain experts and questionnaire
    surveys. This research aims to organize the practical experiences in the domain and to provide a
    guide for future household sewerage pipes connections using indefinite delivery contracts in order
    to reduce possible disputes and guarantee smoother project implementation.
    顯示於類別:[營建管理研究所碩士在職專班] 博碩士論文

    文件中的檔案:

    檔案 描述 大小格式瀏覽次數
    index.html0KbHTML687檢視/開啟


    在NCUIR中所有的資料項目都受到原著作權保護.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明