中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/81784
English  |  正體中文  |  简体中文  |  全文筆數/總筆數 : 80990/80990 (100%)
造訪人次 : 42734704      線上人數 : 1416
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜尋範圍 查詢小技巧:
  • 您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
  • 若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
  • 進階搜尋


    請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/81784


    題名: 地質鑽探報告與地下管線推進工程風險分配之探討;Risk Allocation in Jacking Method for Underground Lines Based on Geotechnical Investigation Report
    作者: 呂嘉坤;Lu, Jia-Kun
    貢獻者: 營建管理研究所在職專班
    關鍵詞: 地質鑽探;推進工法;風險分配
    日期: 2019-07-24
    上傳時間: 2019-09-03 17:01:51 (UTC+8)
    出版者: 國立中央大學
    摘要: 工地之地質現況與鑽探報告有所差異,常為工程上展延工期或變更設計之事由。造假或錯誤之地質鑽探報告固然為爭議之原因,但鑽探技術受設備侷限,縱使鑽探報告依正確之操作方法作成,其探測之結果與實際地質仍可能存在差異。將地質風險由廠商負擔的契約條款,或要求廠商應進行補充鑽探,或根據現場挖掘狀況,事先選用適當切削機具,或於施工中更換適當機具等,如此造成的應變成本由廠商負擔是否合理,容有疑問。
    為探討地質鑽探報告對於推進工程可能造成之風險負擔,本研究嘗試藉由文獻回顧,蒐集契約及施工規範、案例等,認識地質鑽探報告在地下管線推進工程之風險。在蒐集、分析10個地下管線工程案例後,本研究建議在現有契約範本之基礎上,加以「業主提供的鑽探報告在技術上是否錯誤」及地質報告未呈現出之資訊是否為「不可預見」作為區分條件,以作為重大差異之輔助判准,為此,本研究試擬一契約條款,期能補充現有的契約條款,以提升分擔地質風險之公平性。;Differences between site conditions and that shown in the geotechnical investigation report are reasons often seen that cause extensions of time or design changes. A false or wrong geotechnical investigation report is always an unavoidable reason leading to dispute. However, even though the geotechnical investigation report was made based on valid methods, the differences may still exist. In such case, it is questionable when the contract clauses require the contractor take the burdens of additional geotechnical investigation, changing of appropriate drill heads, etc.
    This research explores the issues of risk allocation for using jacking method in underground lines based on a geotechnical investigation report. Literature review including collection of construction specifications, contracts, and dispute cases were conducted in this research to distinguish possible risks. Ten dispute cases were collected and analyzed to summarize two suggestions that assist in awarding differing site conditions in the current model contract. These suggestions are “if the investigation method is technically incorrect in the geotechnical investigation report,” and “site conditions are unforeseeable for an experienced contractor.” Finally, this research proposes an additional clause in the model contract to facilitate a fair distribution of the risks between the contractor and the owner.
    顯示於類別:[營建管理研究所碩士在職專班] 博碩士論文

    文件中的檔案:

    檔案 描述 大小格式瀏覽次數
    index.html0KbHTML260檢視/開啟


    在NCUIR中所有的資料項目都受到原著作權保護.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明